Installation and commissioning of low-current systems — fire alarm, CCTV, access control and data infrastructure — for Baku's arena.

Role
Low-current systems specialist
Team
Armada Mühendislik
Period
2012
Location
Baku, Azerbaijan
Systems
Fire alarm · CCTV · access · data
Setting
Arena, tight schedule

01 / Scope A-170.1

What I was responsible for.

  • Fire alarm
  • CCTV
  • Access control
  • Data infrastructure
  • Coordination with multidisciplinary teams

02 / System A-170.2

How the parts connect.

Security room Network core BUS Fire alarm Panel Detectors Call points CCTV Recorder Cameras Monitors Access control Controllers Readers Door hardware
Fig / A-170.2 — System overviewIllustrative · not the as-built topology

03 / The building A-170.3

The building — in context.

Openly licensed photographs of the building, credited to their authors. They show the place, not my own site record.

Crystal Hall under construction on the Baku shoreline in March 2012, its steel roof frame beside the State Flag Square.
Fig / A-170.3a — Under construction, 25 March 2012 Photo: Frode H. Korneliussen, CC BY-SA 4.0, via Wikimedia Commons
The finished Crystal Hall and the State Flag Square seen from the water, 2012.
Fig / A-170.3b — Finished, with the State Flag Square, 2012 Photo: Patriot Kor, CC BY-SA 4.0, via Wikimedia Commons