← A-110 · In the fieldCase study · A-150

Port Baku Tower 2

Building management and FM200 gaseous fire suppression, delivered by the Nareks MMC technical department.

Role
Head of the Technical Department
Team
Nareks MMC
Period
2018 →
Location
Baku, Azerbaijan
Systems
BMS · FM200 suppression
Standards
EN · NFPA

01 / Scope A-150.1

What I was responsible for.

  • Building management system
  • FM200 gaseous fire suppression
  • Commissioning and functional testing
  • Client handover and training

02 / System A-150.2

How the parts connect.

BMS workstation FM200 control panel BUS Plant controllers AHU Chillers Pumps Floor controllers FCU Lighting Meters Suppression zone Detectors Cylinders Abort / release
Fig / A-150.2 — System overviewIllustrative · not the as-built topology

03 / The building A-150.3

The building — in context.

Openly licensed photographs of the building, credited to their authors. They show the place, not my own site record.

Port Baku district at night in 2014, a tower still under construction on the left.
Fig / A-150.3a — Port Baku district, 2014 Photo: Marco Monelli, CC BY-SA 3.0, via Wikimedia Commons